Market announcement
Eesti Energia AS
LEI code
5493005044RTLQ5RZU70
Size of the entity
Large group
Economic activities
Electricity, Gas, Steam and Air Conditioning Supply, Telecommunication, Computer Programming, Consulting, Computing Infrastructure, and other Information Service Activities, Real Estate Activities, Professional, Scientific and Technical Activities
Country of registered office
Estonia
General information
Categories
Press release
Unique data record identifier
17968
Submission date and time
18.11.2025 14:33:39
Content of announcement in Estonian
Title
Eesti Energia tütarettevõtte Enefit Industry gaasielektrijaama ehitushanke võitis Baran International Ltd ja Baran Group Ltd ühispakkumine
Message
Täna, 18. Novembril 2025, sõlmisid Enefit Industry ja Baran International Ltd ning Baran Group Ltd võtmed-kätte hankelepingu 100-megavatise vesinikuvõimekusega soojuselektrijaama rajamiseks. Hanke maksumus on 100 miljonit eurot. Narva lähistele rajatav gaasielektrijaam hakkab tarnima elektrivõrku kuni 100 MW elektrienergiat ja 85 MW soojust Narva soojusvõrku. Jaam hakkab töötama peamiselt maagaasil või biometaanil ja võimaldab kütusena kasutada kuni 25% vesinikku. Järgmise sammuna algab elektrijaama projekteerimine. Ehituseks läheb indikatiivselt järgmise aasta sügisel. Elektrijaam on planeeritud valmima 2028. aastal ja see plaanitakse rajada Eleringi välja kuulutatud sagedusreservi hanke vastu. Danel Freiberg Treasury- ja finantsriskijuht Eesti Energia AS Tel: +372 5594 3838 E-post: [email protected] (mailto:[email protected])
Content of announcement in English
Title
Baran International Ltd and Baran Group Ltd joint bid wins Enefit Industry’s gas-fired power plant construction tender
Message
Today, 18 November 2025, Enefit Industry signed a turnkey contract with Baran International Ltd and Baran Group Ltd for the construction of a 100 MW combined heat and power plant with hydrogen capability. The contract value is EUR100 million. The new combined gas-fired power plant, to be built near Narva, will supply up to 100 MW of electricity to the grid and 85 MW of heat to the Narva district heating network. The plant will primarily operate on natural gas or biomethane and will be capable of using up to 25% hydrogen as part of its fuel mix. The next step will be the design phase of the power plant. Construction is expected to start in the autumn of next year, and the plant is scheduled to be completed in 2028. The project is planned to be developed in response to the frequency reserve tender announced by Elering. Danel Freiberg Head of Treasury and Financial Risk Management Eesti Energia AS Lelle 22, 11318 Tallinn Phone: +372 5594 3838 Email: [email protected]