Tallinna Vesi signed a contract today for the partial reconstruction of the
mechanical treatment process stage at the wastewater treatment plant in
Paljassaare. The contract was awarded to RVT Ehitus OÜ and Osaühing Mapri Ehitus
who submitted a joint tender. The total cost of the project will be EUR7.6
million, which was the result of a competitive tender.
The reconstruction mainly focuses at increasing the reliability of the
mechanical treatment stage within the wastewater treatment process. The works
will include the construction of the new grit separation tanks and the
associated facilities, and also upgrading the existing technological equipment.
The planned timeline for completion of the project is Q4 2022.
Eliis Vennik
Head of Customer Relations and Communication
Tallinna Vesi
(+372) 626 2275
Eliis.vennik@tvesi.ee
|